Network Rail

Portakabin built a 1650m2, three storey building included offices, mess rooms, toilets and showers for up to 130 people

Requirement

Major refurbishment work at London Bridge station as part of the Thameslink project meant that Network Rail’s maintenance building had to be demolished. With space in short supply in central London, Network Rail identified a suitable site for a new Maintenance Delivery Unit (MDU) at its Southwark depot. However, the site posed a significant challenge for any building supplier, being located above arches on a viaduct surrounded by buildings and busy railway lines.

Solution

Sarah Parr, Network Rail Project Manager, says: “We chose Portakabin to supply the new MDU building because they understood the challenges of the site very well, having built the adjacent project offices, and their building quality and service assurances met all of our requirements. A modular building was perfect for this tricky location, since it requires minimal groundworks, generates almost no waste and requires fewer material deliveries to site.”

Portakabin worked closely with Network Rail to develop a building that overcame the restrictions of the site but also delivered office and welfare facilities of the highest standard. The 1650m2, three storey building included offices, mess rooms, toilets and showers for up to 130 people.

This was certainly not a straightforward job. I was particularly concerned about the two-stage lifting process so close to other buildings, but Portakabin took it all in their stride and completed the job safely and professionally within a week. The effort that Portakabin put into completing such a complex project right on schedule, despite all the extras we added, was tremendous.

Sarah Parr

Network Rail Project Manager, Network Rail